Project Details - CROSS, Domestic Biogas


Client Name Community Reconstruction of Social Service (CROSS)
State Andhra Pradesh
Project Title CROSS Biogas CDM Project
Project Description CROSS will build 5,000 domestic biogas units for as many families in Chittoor district
Technology Domestic Biogas
Units 5,000
Families 5,000
Methodology AMS-I.E. Switch from Non-Renewable Biomass for Thermal Applications by the User
Estimated Annual ERs 15,000
CDM Contact Bhupathy

Started On 10 January 2011
Activity Processes Touched 11 of 15
Tasks Completed 69 of 140

Task Log

ProcessJobTaskStartEndStakeholderReason
11. Obtaining Gold Standard Certification 11.4. Review of the Stakeholder Meeting Report 11.4.1. Receive Comments & Feedbacks from the Gold Standard 18 Apr 1218 Apr 12 Project Proponent  
11. Obtaining Gold Standard Certification 11.3. Open Account at the GS Registry 11.3.4. Upload GS Stakeholders Meeting Report onto the GS Registry 9 Apr 129 Apr 12 Project Proponent  
11. Obtaining Gold Standard Certification 11.2. Prepare GS Stakeholders Meeting Report 11.2.5. Prepare Sustainable Development Matrix 1 Jan 126 Apr 12 Tech Team  
11. Obtaining Gold Standard Certification 11.2. Prepare GS Stakeholders Meeting Report 11.2.6. Finalise the GS Stakeholder Meeting Report 13 Jan 126 Apr 12 Tech Team  
13. Obtaining Host Country Approval 13.1. Submit PIN & PDD to MoEF 13.1.1. Prepare Project Idea Note (PIN) 20 Mar 122 Apr 12 Tech Team  
11. Obtaining Gold Standard Certification 11.3. Open Account at the GS Registry 11.3.3. Send Signed Copies of GS Agreement to GS Registry 14 Mar 1221 Mar 12 Project Proponent  
14. Validating the PDD 14.1. Appoint a DOE 14.1.3. Submit the PDD for Validation 15 Mar 1215 Mar 12 Project Proponent  
12. Finalising PDD 12.1. Finalise the PDD 12.1.2. Revise PDD based on NGO Feedback 10 Mar 1213 Mar 12 Tech Team  
11. Obtaining Gold Standard Certification 11.3. Open Account at the GS Registry 11.3.1. Explain Procedure to Open an Account at the GS Registry 13 Mar 1213 Mar 12 Tech Team  
11. Obtaining Gold Standard Certification 11.3. Open Account at the GS Registry 11.3.2. Open the Account 13 Mar 1213 Mar 12 Project Proponent  
12. Finalising PDD 12.1. Finalise the PDD 12.1.1. Finalise all Sections of the PDD & Submit to Project Proponent 1 Jun 119 Mar 12 Tech Team  
14. Validating the PDD 14.1. Appoint a DOE 14.1.2. Appoint a DOE for the project 27 Feb 127 Mar 12 Project Proponent  
8. Proving Additionality (PDD) 8.3. Address Technology Barrier 8.3.1. Make a Literature Scan 24 May 117 Mar 12 Tech Team  
4. Determining Baseline (PDD) 4.4. Calculate expected CERs for the Project 4.4.2. Calculate the emission reduction potential for the project activity 3 Feb 1229 Feb 12 Tech Team  
14. Validating the PDD 14.1. Appoint a DOE 14.1.1. Advise the Project Proponent on Strengths, Capabilities, Fees, etc. of various Validators 25 Feb 1227 Feb 12 Tech Team  
6. Developing Monitoring Plan (PDD) 6.2. Institutional Structure for Monitoring 6.2.1. Describe Institutional Structure of NGO 7 Feb 129 Feb 12 Project Proponent  
6. Developing Monitoring Plan (PDD) 6.2. Institutional Structure for Monitoring 6.2.2. Describe Management Plan for Monitoring 7 Feb 129 Feb 12 Project Proponent  
6. Developing Monitoring Plan (PDD) 6.2. Institutional Structure for Monitoring 6.2.3. Describe Roles & Responsibilities of Monitoring Team 5 Feb 129 Feb 12 Project Proponent  
6. Developing Monitoring Plan (PDD) 6.1. Determine Monitoring Parameters 6.1.1. List Monitoring Parameters 24 Jan 1227 Jan 12 Tech Team  
6. Developing Monitoring Plan (PDD) 6.1. Determine Monitoring Parameters 6.1.2. Determine Monitoring Frequency for these Parameters 24 Jan 1227 Jan 12 Tech Team  
6. Developing Monitoring Plan (PDD) 6.1. Determine Monitoring Parameters 6.1.3. Determine Monitoring Duration of Project Activity 24 Jan 1227 Jan 12 Tech Team  
6. Developing Monitoring Plan (PDD) 6.1. Determine Monitoring Parameters 6.1.4. Determine Maintainence & Servicing Mechanism of the Technology 24 Jan 1227 Jan 12 CDM Preparation Team  
9. Determining Project Duration (PDD) 9.1. Address Project Duration Issues 9.1.1. Anticipate a Realistic Start Date for the CDM Project 24 Jan 1226 Jan 12 Project Proponent  
11. Obtaining Gold Standard Certification 11.2. Prepare GS Stakeholders Meeting Report 11.2.1. Provide Proof of Invitation 11 Jan 1225 Jan 12 CDM Preparation Team  
11. Obtaining Gold Standard Certification 11.2. Prepare GS Stakeholders Meeting Report 11.2.2. Provide Photos of the GS Stakeholders Meeting(s) 11 Jan 1225 Jan 12 CDM Preparation Team  
123