| Process | Job | Task | Start | End | Stakeholder | Reason |
|
11. Obtaining Gold Standard Certification
|
11.4. Review of the Stakeholder Meeting Report
|
11.4.1. Receive Comments & Feedbacks from the Gold Standard
| 18 Apr 12 | 18 Apr 12 |
Project Proponent
| |
|
11. Obtaining Gold Standard Certification
|
11.3. Open Account at the GS Registry
|
11.3.4. Upload GS Stakeholders Meeting Report onto the GS Registry
| 9 Apr 12 | 9 Apr 12 |
Project Proponent
| |
|
11. Obtaining Gold Standard Certification
|
11.2. Prepare GS Stakeholders Meeting Report
|
11.2.5. Prepare Sustainable Development Matrix
| 1 Jan 12 | 6 Apr 12 |
Tech Team
| |
|
11. Obtaining Gold Standard Certification
|
11.2. Prepare GS Stakeholders Meeting Report
|
11.2.6. Finalise the GS Stakeholder Meeting Report
| 13 Jan 12 | 6 Apr 12 |
Tech Team
| |
|
13. Obtaining Host Country Approval
|
13.1. Submit PIN & PDD to MoEF
|
13.1.1. Prepare Project Idea Note (PIN)
| 20 Mar 12 | 2 Apr 12 |
Tech Team
| |
|
11. Obtaining Gold Standard Certification
|
11.3. Open Account at the GS Registry
|
11.3.3. Send Signed Copies of GS Agreement to GS Registry
| 14 Mar 12 | 21 Mar 12 |
Project Proponent
| |
|
14. Validating the PDD
|
14.1. Appoint a DOE
|
14.1.3. Submit the PDD for Validation
| 15 Mar 12 | 15 Mar 12 |
Project Proponent
| |
|
12. Finalising PDD
|
12.1. Finalise the PDD
|
12.1.2. Revise PDD based on NGO Feedback
| 10 Mar 12 | 13 Mar 12 |
Tech Team
| |
|
11. Obtaining Gold Standard Certification
|
11.3. Open Account at the GS Registry
|
11.3.1. Explain Procedure to Open an Account at the GS Registry
| 13 Mar 12 | 13 Mar 12 |
Tech Team
| |
|
11. Obtaining Gold Standard Certification
|
11.3. Open Account at the GS Registry
|
11.3.2. Open the Account
| 13 Mar 12 | 13 Mar 12 |
Project Proponent
| |
|
12. Finalising PDD
|
12.1. Finalise the PDD
|
12.1.1. Finalise all Sections of the PDD & Submit to Project Proponent
| 1 Jun 11 | 9 Mar 12 |
Tech Team
| |
|
14. Validating the PDD
|
14.1. Appoint a DOE
|
14.1.2. Appoint a DOE for the project
| 27 Feb 12 | 7 Mar 12 |
Project Proponent
| |
|
8. Proving Additionality (PDD)
|
8.3. Address Technology Barrier
|
8.3.1. Make a Literature Scan
| 24 May 11 | 7 Mar 12 |
Tech Team
| |
|
4. Determining Baseline (PDD)
|
4.4. Calculate expected CERs for the Project
|
4.4.2. Calculate the emission reduction potential for the project activity
| 3 Feb 12 | 29 Feb 12 |
Tech Team
| |
|
14. Validating the PDD
|
14.1. Appoint a DOE
|
14.1.1. Advise the Project Proponent on Strengths, Capabilities, Fees, etc. of various Validators
| 25 Feb 12 | 27 Feb 12 |
Tech Team
| |
|
6. Developing Monitoring Plan (PDD)
|
6.2. Institutional Structure for Monitoring
|
6.2.1. Describe Institutional Structure of NGO
| 7 Feb 12 | 9 Feb 12 |
Project Proponent
| |
|
6. Developing Monitoring Plan (PDD)
|
6.2. Institutional Structure for Monitoring
|
6.2.2. Describe Management Plan for Monitoring
| 7 Feb 12 | 9 Feb 12 |
Project Proponent
| |
|
6. Developing Monitoring Plan (PDD)
|
6.2. Institutional Structure for Monitoring
|
6.2.3. Describe Roles & Responsibilities of Monitoring Team
| 5 Feb 12 | 9 Feb 12 |
Project Proponent
| |
|
6. Developing Monitoring Plan (PDD)
|
6.1. Determine Monitoring Parameters
|
6.1.1. List Monitoring Parameters
| 24 Jan 12 | 27 Jan 12 |
Tech Team
| |
|
6. Developing Monitoring Plan (PDD)
|
6.1. Determine Monitoring Parameters
|
6.1.2. Determine Monitoring Frequency for these Parameters
| 24 Jan 12 | 27 Jan 12 |
Tech Team
| |
|
6. Developing Monitoring Plan (PDD)
|
6.1. Determine Monitoring Parameters
|
6.1.3. Determine Monitoring Duration of Project Activity
| 24 Jan 12 | 27 Jan 12 |
Tech Team
| |
|
6. Developing Monitoring Plan (PDD)
|
6.1. Determine Monitoring Parameters
|
6.1.4. Determine Maintainence & Servicing Mechanism of the Technology
| 24 Jan 12 | 27 Jan 12 |
CDM Preparation Team
| |
|
9. Determining Project Duration (PDD)
|
9.1. Address Project Duration Issues
|
9.1.1. Anticipate a Realistic Start Date for the CDM Project
| 24 Jan 12 | 26 Jan 12 |
Project Proponent
| |
|
11. Obtaining Gold Standard Certification
|
11.2. Prepare GS Stakeholders Meeting Report
|
11.2.1. Provide Proof of Invitation
| 11 Jan 12 | 25 Jan 12 |
CDM Preparation Team
| |
|
11. Obtaining Gold Standard Certification
|
11.2. Prepare GS Stakeholders Meeting Report
|
11.2.2. Provide Photos of the GS Stakeholders Meeting(s)
| 11 Jan 12 | 25 Jan 12 |
CDM Preparation Team
| |
|