| Process | Job | Task | Start | End | Stakeholder | Reason |
|
15. Registration
|
15.3. Webhost for Registration
|
15.3.1. 4 weeks Webhosting for SSC projects
| 28 May 11 | 24 Jun 11 |
UNFCCC
| |
|
15. Registration
|
15.3. Webhost for Registration
|
15.3.5. PDD Registered
| 24 Jun 11 | 24 Jun 11 |
UNFCCC
| |
|
15. Registration
|
15.2. Completeness Check
|
15.2.1. Webhost for Completeness Check
| 25 Mar 11 | 1 Apr 11 |
UNFCCC
| |
|
15. Registration
|
15.2. Completeness Check
|
15.2.2. Answer Queries, if any, by Revising PDD
| 1 Apr 11 | 1 Apr 11 |
Tech Team
| |
|
15. Registration
|
15.1. Registration Fee
|
15.1.2. Pay the CDM Registration Fee to the E.B., UNFCCC
| 24 Feb 11 | 24 Feb 11 |
Project Proponent
| |
|
15. Registration
|
15.1. Registration Fee
|
15.1.1. Webhost for Paying Registration Fee & send Email
| 14 Feb 11 | 14 Feb 11 |
UNFCCC
| |
|
14. Validating the PDD
|
14.4. Modalities of Communication (MoC)
|
14.4.2. Submit PDD, Validation Report and MoC to the E.B., UNFCCC
| 10 Feb 11 | 10 Feb 11 |
Project Proponent
| |
|
14. Validating the PDD
|
14.4. Modalities of Communication (MoC)
|
14.4.1. Choose Contact Person(s) for Modalities of Communication and Submit Form to DOE
| 8 Feb 11 | 8 Feb 11 |
Project Proponent
| |
|
14. Validating the PDD
|
14.3. Draft Validation Report
|
14.3.7. Issue Final Validation Report
| 2 Feb 11 | 2 Feb 11 |
DOE
| |
|
11. Obtaining Gold Standard Certification
|
11.5. GS Passport & Feedback
|
11.5.2. Webhost GS Stakeholder Meeting Report and Draft Passport Report for public comments for 60 days
| 5 Oct 10 | 6 Dec 10 |
Project Proponent
| |
|
14. Validating the PDD
|
14.3. Draft Validation Report
|
14.3.6. Respond to Queries & Revise PDD based on Technical Review
| 14 Nov 10 | 14 Nov 10 |
Tech Team
| |
|
14. Validating the PDD
|
14.3. Draft Validation Report
|
14.3.5. Technical Review of PDD
| 12 Nov 10 | 12 Nov 10 |
DOE
| |
|
11. Obtaining Gold Standard Certification
|
11.5. GS Passport & Feedback
|
11.5.1. Prepare GS Passport
| 24 Jun 10 | 30 Sep 10 |
Tech Team
| |
|
14. Validating the PDD
|
14.3. Draft Validation Report
|
14.3.2. Prepare Additional Documents & Provide Information to answer CLs and CARs
| 3 Sep 10 | 19 Sep 10 |
Tech Team
| |
|
14. Validating the PDD
|
14.3. Draft Validation Report
|
14.3.3. Respond to Clarifications (CLs) and Corrective Action Requests (CARs)
| 3 Sep 10 | 19 Sep 10 |
Tech Team
| |
|
14. Validating the PDD
|
14.3. Draft Validation Report
|
14.3.4. Revise PDD based on Draft Validation Report, CLs & CARs
| 3 Sep 10 | 19 Sep 10 |
Tech Team
| |
|
14. Validating the PDD
|
14.3. Draft Validation Report
|
14.3.1. Receive Draft Validation Report
| 2 Sep 10 | 2 Sep 10 |
Tech Team
| |
|
13. Obtaining Host Country Approval
|
13.2. Attend Personal Interview with Designated National
|
13.2.6. Grant Host Country Approval
| 18 Aug 10 | 18 Aug 10 |
DNA
| |
|
14. Validating the PDD
|
14.2. Site Visit
|
14.2.3. Accompany the DOE on Site Visit
| 19 Jul 10 | 21 Jul 10 |
Project Proponent & Tech Team
| |
|
14. Validating the PDD
|
14.2. Site Visit
|
14.2.2. List Desk Review Documents required during Site Visit
| 12 Jul 10 | 18 Jul 10 |
Tech Team
| |
|
14. Validating the PDD
|
14.2. Site Visit
|
14.2.1. Communicate Date & Agenda for Site Visit
| 22 Jun 10 | 22 Jun 10 |
DOE
| |
|
13. Obtaining Host Country Approval
|
13.2. Attend Personal Interview with Designated National
|
13.2.5. Prepare & Submit Additional Documents, if required
| 15 Jun 10 | 15 Jun 10 |
Tech Team
| |
|
11. Obtaining Gold Standard Certification
|
11.4. Review of the Stakeholder Meeting Report
|
11.4.3. Upload Revised GS Stakeholders Meeting Report onto the GS Registry
| 10 Jun 10 | 10 Jun 10 |
Project Proponent
| |
|
11. Obtaining Gold Standard Certification
|
11.4. Review of the Stakeholder Meeting Report
|
11.4.2. Address Issues Raised & Revise GS Stakeholder Meeting Report accordingly
| 27 May 10 | 27 May 10 |
Tech Team
| |
|
11. Obtaining Gold Standard Certification
|
11.4. Review of the Stakeholder Meeting Report
|
11.4.1. Receive Comments & Feedbacks from the Gold Standard
| 20 May 10 | 20 May 10 |
Project Proponent
| |
|