Project Details - THREAD, Photovoltaic Lamps


Client Name Team for Human Resource Education & Action for Dev (THREAD)
State Orissa
Project Title THREAD Solar PhotoVoltaic CDM Project
Project Description THREAD is exploring the feasibility of providing 3 solar photovoltaic lamps each, to 110,000 Tribal families in Orissa Unfortunately, the Emission Reductions per lamp are so low that the financials do not work out. So the project has temporarily been put on hold, till a favourable change occurs in the Methodology.
Technology Photovoltaic Lamps
Units 330,000
Families 110,000
Methodology AMS-I.A. Electricity generation by the User
Estimated Annual ERs 26,400
CDM Contact G. John

Started On 25 May 2009
Activity Processes Touched 10 of 15
Tasks Completed 101 of 140

Task Log

ProcessJobTaskStartEndStakeholderReason
3. Collecting Demographic Data 3.3. Collect Demographic Data 3.3.2. Enter Data into the Module & Retain Survey Sheets till Validation 15 Dec 0915 Jun 10 CDM Preparation Team Estimated time frame from PP
11. Obtaining Gold Standard Certification 11.4. Review of the Stakeholder Meeting Report 11.4.1. Receive Comments & Feedbacks from the Gold Standard 27 May 1028 May 10 Sandeep Loya  
11. Obtaining Gold Standard Certification 11.4. Review of the Stakeholder Meeting Report 11.4.2. Address Issues Raised & Revise GS Stakeholder Meeting Report accordingly 27 May 1028 May 10 Tech Team  
11. Obtaining Gold Standard Certification 11.4. Review of the Stakeholder Meeting Report 11.4.3. Upload Revised GS Stakeholders Meeting Report onto the GS Registry 28 May 1028 May 10 Sandeep Loya  
11. Obtaining Gold Standard Certification 11.3. Open Account at the GS Registry 11.3.4. Upload GS Stakeholders Meeting Report onto the GS Registry 6 May 106 May 10 Sandeep Loya  
8. Proving Additionality (PDD) 8.5. Address Other Barriers 8.5.1. Make a Literature Scan and Apply Wild Imagination 24 Apr 1025 Apr 10 Sandeep Loya  
8. Proving Additionality (PDD) 8.4. Address Barriers due to Prevailing Practices 8.4.1. Map the Sociocultural Behavioural Patterns of Participating Families 17 Apr 1022 Apr 10 Sandeep Loya More support data for the argument
8. Proving Additionality (PDD) 8.3. Address Technology Barrier 8.3.2. Prove Technology Barrier through a Macro Survey 17 Apr 1020 Apr 10 Sandeep Loya More technology alternatives and statistics
6. Developing Monitoring Plan (PDD) 6.2. Institutional Structure for Monitoring 6.2.3. Describe Roles & Responsibilities of Monitoring Team 16 Apr 1019 Apr 10 Sandeep Loya  
6. Developing Monitoring Plan (PDD) 6.2. Institutional Structure for Monitoring 6.2.2. Describe Management Plan for Monitoring 14 Apr 1016 Apr 10 Sandeep Loya  
6. Developing Monitoring Plan (PDD) 6.2. Institutional Structure for Monitoring 6.2.1. Describe Institutional Structure of NGO 13 Apr 1014 Apr 10 Sandeep Loya  
9. Determining Project Duration (PDD) 9.1. Address Project Duration Issues 9.1.2. Assess the Operational Lifetime of the Chosen Technology 13 Apr 1014 Apr 10 Sandeep Loya  
9. Determining Project Duration (PDD) 9.1. Address Project Duration Issues 9.1.3. Choose the Crediting Period for the Project Activity 13 Apr 1014 Apr 10 Sandeep Loya  
6. Developing Monitoring Plan (PDD) 6.1. Determine Monitoring Parameters 6.1.4. Determine Maintainence & Servicing Mechanism of the Technology 12 Apr 1013 Apr 10 Sandeep Loya  
6. Developing Monitoring Plan (PDD) 6.1. Determine Monitoring Parameters 6.1.1. List Monitoring Parameters 10 Apr 1012 Apr 10 Sandeep Loya  
6. Developing Monitoring Plan (PDD) 6.1. Determine Monitoring Parameters 6.1.2. Determine Monitoring Frequency for these Parameters 10 Apr 1012 Apr 10 Sandeep Loya  
6. Developing Monitoring Plan (PDD) 6.1. Determine Monitoring Parameters 6.1.3. Determine Monitoring Duration of Project Activity 10 Apr 1012 Apr 10 Sandeep Loya  
9. Determining Project Duration (PDD) 9.1. Address Project Duration Issues 9.1.1. Anticipate a Realistic Start Date for the CDM Project 6 Apr 106 Apr 10 Project Proponent & Tech Team  
4. Determining Baseline (PDD) 4.4. Calculate expected CERs for the Project 4.4.2. Calculate the emission reduction potential for the project activity 12 Mar 1022 Mar 10 Tech Team  
4. Determining Baseline (PDD) 4.4. Calculate expected CERs for the Project 4.4.2. Calculate the emission reduction potential for the project activity 12 Mar 1022 Mar 10 Tech Team  
4. Determining Baseline (PDD) 4.1. Scan Literature 4.1.3. Collect District Level Statistics 8 Mar 1016 Mar 10 Project Proponent & Tech Team  
4. Determining Baseline (PDD) 4.4. Calculate expected CERs for the Project 4.4.1. Analyse Baseline Data for PDD 27 Feb 1011 Mar 10 Sandeep Loya  
4. Determining Baseline (PDD) 4.2. Design Sample Survey Format 4.2.6. Analyse the data 2 Mar 109 Mar 10 Sandeep Loya  
3. Collecting Demographic Data 3.3. Collect Demographic Data 3.3.1. Collect Household Data 24 Nov 099 Mar 10 CDM Preparation Team Collect SPV & ICS household data with baseline
3. Collecting Demographic Data 3.3. Collect Demographic Data 3.3.3. Analyse Data for PDD 23 Feb 1027 Feb 10 Sandeep Loya  