| Process | Job | Task | Start | End | Stakeholder | Reason |
|
3. Collecting Demographic Data
|
3.3. Collect Demographic Data
|
3.3.2. Enter Data into the Module & Retain Survey Sheets till Validation
| 15 Dec 09 | 15 Jun 10 |
CDM Preparation Team
| Estimated time frame from PP |
|
11. Obtaining Gold Standard Certification
|
11.4. Review of the Stakeholder Meeting Report
|
11.4.1. Receive Comments & Feedbacks from the Gold Standard
| 27 May 10 | 28 May 10 |
Sandeep Loya
| |
|
11. Obtaining Gold Standard Certification
|
11.4. Review of the Stakeholder Meeting Report
|
11.4.2. Address Issues Raised & Revise GS Stakeholder Meeting Report accordingly
| 27 May 10 | 28 May 10 |
Tech Team
| |
|
11. Obtaining Gold Standard Certification
|
11.4. Review of the Stakeholder Meeting Report
|
11.4.3. Upload Revised GS Stakeholders Meeting Report onto the GS Registry
| 28 May 10 | 28 May 10 |
Sandeep Loya
| |
|
11. Obtaining Gold Standard Certification
|
11.3. Open Account at the GS Registry
|
11.3.4. Upload GS Stakeholders Meeting Report onto the GS Registry
| 6 May 10 | 6 May 10 |
Sandeep Loya
| |
|
8. Proving Additionality (PDD)
|
8.5. Address Other Barriers
|
8.5.1. Make a Literature Scan and Apply Wild Imagination
| 24 Apr 10 | 25 Apr 10 |
Sandeep Loya
| |
|
8. Proving Additionality (PDD)
|
8.4. Address Barriers due to Prevailing Practices
|
8.4.1. Map the Sociocultural Behavioural Patterns of Participating Families
| 17 Apr 10 | 22 Apr 10 |
Sandeep Loya
| More support data for the argument |
|
8. Proving Additionality (PDD)
|
8.3. Address Technology Barrier
|
8.3.2. Prove Technology Barrier through a Macro Survey
| 17 Apr 10 | 20 Apr 10 |
Sandeep Loya
| More technology alternatives and statistics |
|
6. Developing Monitoring Plan (PDD)
|
6.2. Institutional Structure for Monitoring
|
6.2.3. Describe Roles & Responsibilities of Monitoring Team
| 16 Apr 10 | 19 Apr 10 |
Sandeep Loya
| |
|
6. Developing Monitoring Plan (PDD)
|
6.2. Institutional Structure for Monitoring
|
6.2.2. Describe Management Plan for Monitoring
| 14 Apr 10 | 16 Apr 10 |
Sandeep Loya
| |
|
6. Developing Monitoring Plan (PDD)
|
6.2. Institutional Structure for Monitoring
|
6.2.1. Describe Institutional Structure of NGO
| 13 Apr 10 | 14 Apr 10 |
Sandeep Loya
| |
|
9. Determining Project Duration (PDD)
|
9.1. Address Project Duration Issues
|
9.1.2. Assess the Operational Lifetime of the Chosen Technology
| 13 Apr 10 | 14 Apr 10 |
Sandeep Loya
| |
|
9. Determining Project Duration (PDD)
|
9.1. Address Project Duration Issues
|
9.1.3. Choose the Crediting Period for the Project Activity
| 13 Apr 10 | 14 Apr 10 |
Sandeep Loya
| |
|
6. Developing Monitoring Plan (PDD)
|
6.1. Determine Monitoring Parameters
|
6.1.4. Determine Maintainence & Servicing Mechanism of the Technology
| 12 Apr 10 | 13 Apr 10 |
Sandeep Loya
| |
|
6. Developing Monitoring Plan (PDD)
|
6.1. Determine Monitoring Parameters
|
6.1.1. List Monitoring Parameters
| 10 Apr 10 | 12 Apr 10 |
Sandeep Loya
| |
|
6. Developing Monitoring Plan (PDD)
|
6.1. Determine Monitoring Parameters
|
6.1.2. Determine Monitoring Frequency for these Parameters
| 10 Apr 10 | 12 Apr 10 |
Sandeep Loya
| |
|
6. Developing Monitoring Plan (PDD)
|
6.1. Determine Monitoring Parameters
|
6.1.3. Determine Monitoring Duration of Project Activity
| 10 Apr 10 | 12 Apr 10 |
Sandeep Loya
| |
|
9. Determining Project Duration (PDD)
|
9.1. Address Project Duration Issues
|
9.1.1. Anticipate a Realistic Start Date for the CDM Project
| 6 Apr 10 | 6 Apr 10 |
Project Proponent & Tech Team
| |
|
4. Determining Baseline (PDD)
|
4.4. Calculate expected CERs for the Project
|
4.4.2. Calculate the emission reduction potential for the project activity
| 12 Mar 10 | 22 Mar 10 |
Tech Team
| |
|
4. Determining Baseline (PDD)
|
4.4. Calculate expected CERs for the Project
|
4.4.2. Calculate the emission reduction potential for the project activity
| 12 Mar 10 | 22 Mar 10 |
Tech Team
| |
|
4. Determining Baseline (PDD)
|
4.1. Scan Literature
|
4.1.3. Collect District Level Statistics
| 8 Mar 10 | 16 Mar 10 |
Project Proponent & Tech Team
| |
|
4. Determining Baseline (PDD)
|
4.4. Calculate expected CERs for the Project
|
4.4.1. Analyse Baseline Data for PDD
| 27 Feb 10 | 11 Mar 10 |
Sandeep Loya
| |
|
4. Determining Baseline (PDD)
|
4.2. Design Sample Survey Format
|
4.2.6. Analyse the data
| 2 Mar 10 | 9 Mar 10 |
Sandeep Loya
| |
|
3. Collecting Demographic Data
|
3.3. Collect Demographic Data
|
3.3.1. Collect Household Data
| 24 Nov 09 | 9 Mar 10 |
CDM Preparation Team
| Collect SPV & ICS household data with baseline |
|
3. Collecting Demographic Data
|
3.3. Collect Demographic Data
|
3.3.3. Analyse Data for PDD
| 23 Feb 10 | 27 Feb 10 |
Sandeep Loya
| |
|