Project Details

IFDP, Domestic Biogas

Client Name CReNIEO - Integrated Fisherfolk Development Project
Short Name IFDP
Client Type Grassroots NGO
Synopsis Member of the SCINDeA network & works among fisherfolk in 30 villages in Pulicat. Has been involved in development work for the last 20 years. In the CDM Biogas project IFDP will be covering 6,000 families in 405 villages.
Website http://www.crenieo.org
Address Old Shell Factory
Ponneri Taluk, Thiruvallur District
City Pulicat
Pin Code 601205
State Tamil Nadu
Project Title IFDP Biogas CDM Project
Project Description Biogas Units to be build in project area
Standard CDM & Gold Standard
Technology Domestic Biogas
Units 6,000
Families 6,000
Methodology AMS-I.E. Switch from Non-Renewable Biomass for Thermal Applications by the User
Estimated Annual ERs 24,000
CDM Contact Meerasa

Started On 11 July 2012
Activity Processes Touched 6 of 15
Tasks Completed 19 of 140

Task Log

ProcessJobTaskStartEndStakeholderReason
15. Registration 15.3. Webhost for Registration 15.3.4. Resubmit Revised PDD to UNFCCC 7 Feb 156 Mar 15 UNFCCC  
15. Registration 15.3. Webhost for Registration 15.3.1. 4 weeks Webhosting for SSC projects 7 Feb 156 Mar 15 UNFCCC  
15. Registration 15.3. Webhost for Registration 15.3.5. PDD Registered 6 Nov 146 Mar 15 UNFCCC  
15. Registration 15.2. Completeness Check 15.2.1. Webhost for Completeness Check 27 Jan 156 Feb 15 UNFCCC  
15. Registration 15.2. Completeness Check 15.2.1. Webhost for Completeness Check 6 Jan 1513 Jan 15 UNFCCC  
15. Registration 15.1. Registration Fee 15.1.1. Webhost for Paying Registration Fee & send Email 24 Oct 1424 Oct 14 UNFCCC  
14. Validating the PDD 14.3. Draft Validation Report 14.3.7. Issue Final Validation Report 6 Oct 146 Oct 14 DOE  
13. Obtaining Host Country Approval 13.2. Attend Personal Interview with Designated National 13.2.6. Grant Host Country Approval 3 Sep 143 Sep 14 DNA  
11. Obtaining Gold Standard Certification 11.5. GS Passport & Feedback 11.5.2. Webhost GS Stakeholder Meeting Report and Draft Passport Report for public comments for 60 days 24 Apr 1425 Jun 14 Project Proponent & Tech Team  
11. Obtaining Gold Standard Certification 11.1. Conduct GS Stakeholder Meeting 11.1.1. Familiarise CDM Team & NGO Staff on Procedure 12 Jun 1412 Jun 14 Tech Team  
14. Validating the PDD 14.3. Draft Validation Report 14.3.1. Receive Draft Validation Report 3 Jun 143 Jun 14 DOE  
14. Validating the PDD 14.2. Site Visit 14.2.3. Accompany the DOE on Site Visit 27 Apr 1428 Apr 14 Project Proponent & Tech Team  
11. Obtaining Gold Standard Certification 11.3. Open Account at the GS Registry 11.3.4. Upload GS Stakeholders Meeting Report onto the GS Registry 6 Feb 146 Feb 14 Tech Team  
14. Validating the PDD 14.1. Appoint a DOE 14.1.3. Submit the PDD for Validation 20 Jan 1420 Jan 14 Tech Team  
11. Obtaining Gold Standard Certification 11.3. Open Account at the GS Registry 11.3.2. Open the Account 21 Nov 1321 Nov 13 Project Proponent & Tech Team  
11. Obtaining Gold Standard Certification 11.2. Prepare GS Stakeholders Meeting Report 11.2.6. Finalise the GS Stakeholder Meeting Report 24 Aug 1320 Nov 13 Tech Team  
11. Obtaining Gold Standard Certification 11.1. Conduct GS Stakeholder Meeting 11.1.9. Conduct GS Stakeholders Meeting(s) 24 Aug 1324 Aug 13 CDM Preparation Team  
3. Collecting Demographic Data 3.2. Obtain Monitoring Solution 3.2.1. Negotiate with Tristle Technologies Pvt. Ltd. 24 Jul 1224 Jul 12 Tristle  
1. Deciding to Undertake CDM 1.3. Decide to Undertake CDM 1.3.3. Sign Service Contract with the FCN Tech Team 23 Jul 1223 Jul 12 Project Proponent  
1. Deciding to Undertake CDM 1.3. Decide to Undertake CDM 1.3.1. Pass Board Resolution to Undertake CDM Project 11 Jul 1211 Jul 12 Project Proponent